Turnaround Time Efficiency In MRO Industry : A DMAIC Based Evaluation Of Gate System Quality Performance at PT. GMF AeroAsia
DOI:
https://doi.org/10.54099/ijamb.v4i1.1473Keywords:
Six Sigma DMAIC, Engine Maintenance, TurnaroundTime, Gate systemAbstract
This research was conducted to evaluate the implementation of gate-based quality control in the engine maintenance process to improve turnaround time (TAT) efficiency in the maintenance process. TAT is a key indicator for assessing operational efficiency in the maintenance, repair, and overhaul (MRO) industry and affects customer satisfaction levels. Based on the operational data of PT. GMF AeroAsia for the period 2022-2024, TAT often does not meet the targets set in the service level agreement (SLA). One of the causes is the delay that occurs at gate 4-5 in the gate system. The research conducted used Six Sigma DMAIC to evaluate and identify the root causes of issues occurring in the maintenance process, as well as to examine the influence of factors such as working capital, external vendor causes, and material procurement related to the delays at gate 4-5. The method used in this research employs both quantitative and qualitative approaches by collecting data through historical data, observations, and interviews. The research results indicate that the implementation of Six Sigma DMAIC at gates 4-5 is not yet optimal, with delays predominantly caused by working capital and external vendor issues. This study found a strong correlation between the frequency of delays and the duration of delays with the total TAT. These findings suggest that the integration of Six Sigma DMAIC, supported by Critical Chain Project Management and Reliability Centered Maintenance, could be a solution to improve the efficiency occurring in the gate 4-5, thereby directly enhancing the TAT efficiency.
References
Ahmad, M., & Wilkins, S. (2024). Purposive sampling in qualitative research: a framework for the entire journey. Quality and Quantity. https://doi.org/10.1007/s11135-024-02022-5
Aziz, A., Mulyanti, R. Y., & Soma, A. M. (2025). International Journal of Multidisciplinary Research of Higher Education (IJMURHICA) Managerial Transformation at Sea: Strategies to Enhance Performance, Motivation and Crew Safety. International Journal of Multidisciplinary Research of Higher Education, 8, 207–219. http://ijmurhica.ppj.unp.ac.id/index.php/ijmurhica
Creswell, J. W. (2018). Qualitative, Quantitative, and Mixed Methods Approaches (5th ed.).
da Silva, R. F., & de Souza, G. F. M. (2022). Modeling a maintenance management framework for asset management based on ISO 55000 series guidelines. Journal of Quality in Maintenance Engineering, 28(4), 915–937. https://doi.org/10.1108/JQME-08-2020-0082
George, darren, & Mallery, P. (2020). IBM SPSS Statistics 26 Step by Step (sixteenth).
Ginting, R., & Fattah, M. G. (2020). Production quality control with new seven tools for defect minimization on PT. Dirgantara Indonesia. IOP Conference Series: Earth and Environmental Science, 452(1). https://doi.org/10.1088/1755-1315/452/1/012082
Gupta, M. C., & Boyd, L. H. (2008). Theory of constraints: A theory for operations management. International Journal of Operations and Production Management, 28(10), 991–1012. https://doi.org/10.1108/01443570810903122
Hendayani, R., & Dharmawan, M. C. (2020). Strategies for Improving the Quality of Logistics Courier Services through Priority Problem-solving Based on Multiclass Classification. IOP Conference Series: Materials Science and Engineering, 879(1). https://doi.org/10.1088/1757-899X/879/1/012051
Jones, M. B., & Dowdall, J. (2022). Lean Six Sigma For Dummies®, 4th Edition (4th ed.). http://www.wiley.com/go/permissions.
Junqueira, V. S. V., Nagano, M. S., & Miyata, H. H. (2020). Procedure structuring for programming aircraft maintenance activities. Revista de Gestao, 27(1), 2–20. https://doi.org/10.1108/REGE-02-2018-0026
Khasanah, R., Jamasri, & Yuniarto, H. A. (2019). Evaluation of turnaround maintenance practice effects in the process industry. IOP Conference Series: Materials Science and Engineering, 673(1). https://doi.org/10.1088/1757-899X/673/1/012097
Leach, L. P. . (2000). Critical chain project management. Artech House.
Lochmiller, C. R. (2021). Conducting thematic analysis with qualitative data. Qualitative Report, 26(6), 2029–2044. https://doi.org/10.46743/2160-3715/2021.5008
MacDonnell, M., & Clegg, B. (2007). Designing a support system for aerospace maintenance supply chains. Journal of Manufacturing Technology Management, 18(2), 139–152. https://doi.org/10.1108/17410380710722863
Maleyef, J. (2022). Quality service management : a guide to improving business processes (1 st). https://doi.org/https://doi.org/10.4324/9781003199014
Manenzhe, M. T., Telukdarie, A., & Munsamy, M. (2023). Maintenance work management process model: incorporating system dynamics and 4IR technologies. Journal of Quality in Maintenance Engineering, 29(5), 88–119. https://doi.org/10.1108/JQME-10-2022-0063
Miles, B. M., Huberman, A. M., & Saldana, J. (2014). Book - Qualitative Data Analysis_ A Methods Sourcebook (3rd ed.). Sage Publications.
Moubrey, J. (2000). BOOK - RCM.
Permana, H. N., & Saifuddin, J. A. (2024). Analysis of packaging quality control of PT. LMN using the seven tools method and new seven tools. Operations Excellence: Journal of Applied Industrial Engineering, 16(2), 135. https://doi.org/10.22441/oe.2024.v16.i2.109
Piercy, N., Caldwell, N., & Rich, N. (2009). Considering connectivity in operations journals. International Journal of Productivity and Performance Management, 58(7), 607–631. https://doi.org/10.1108/17410400910989449
Pokharel, S., & Jiao, J. R. (2008). Turn-around maintenance management in a processing industry: A case study. Journal of Quality in Maintenance Engineering, 14(2), 109–122. https://doi.org/10.1108/13552510810877638
Prashar, A. (2014). Adoption of Six Sigma DMAIC to reduce cost of poor quality. International Journal of Productivity and Performance Management, 63(1), 103–126. https://doi.org/10.1108/IJPPM-01-2013-0018
Rohman, M. M., Bani, M. D., Antonny, G., Aryasatya, B., & Muri, D. (2023). METODE PENELITIAN KUANTITATIF DAN KUALITATIF : TEORI DAN PRAKTIK GET PRESS INDONESIA. https://www.researchgate.net/publication/377329440
Rukajat, A. (2018). PENDEKATAN PENELITIAN KUANTITATIF (QUANTITATIVE RESEARCH APPROACH).
Sadkowski, W., & Jedynak, P. (2022). Quality Management and Accounting in Service Industries; A New Model of Quality Cost Calculation (1 st). https://doi.org/https://doi.org/10.4324/9781003275022
Salama, T., Salah, A., & Moselhi, O. (2021). Integrating critical chain project management with last planner system for linear scheduling of modular construction. Construction Innovation, 21(4), 525–554. https://doi.org/10.1108/CI-05-2018-0046
Siaudzionis Filho, F. A. B., Pontes, H. L. J., Albertin, M. R., de Lima, R. L. M., & Moraes, T. de C. (2018). Application of visual management panel on an airplane assembly station. International Journal of Productivity and Performance Management, 67(6), 1045–1062. https://doi.org/10.1108/IJPPM-09-2016-0189
Stahl, N. A., & King, J. R. (2020). Expanding Approaches for Research: Understanding and Using Trustworthiness in Qualitative Research. Developmental Education, 44(1). https://www.researchgate.net/publication/346425936
Sugiyono. (2013). METODE PENELITIAN KUANTITATIF.
Usman, A., Azis, Y., Harsanto, B., & Azis, A. M. (2022). Airport service quality dimension and measurement: a systematic literature review and future research agenda. International Journal of Quality and Reliability Management, 39(10), 2302–2322. https://doi.org/10.1108/IJQRM-07-2021-0198
Zidane, Y. J. T., & Olsson, N. O. E. (2017). Defining project efficiency, effectiveness and efficacy. In International Journal of Managing Projects in Business (Vol. 10, Issue 3, pp. 621–641). Emerald Group Publishing Ltd. https://doi.org/10.1108/IJMPB-10-2016-0085
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2025 Luthfi Rofif Labiiba, Anton Mulyono Azis

This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License.